The paper presents the use of the Fast-Time navigational simulator to verify the location of
designed elements of navigational infrastructure in vicinity of a high traffic fairway. The aim
of the study is to perform the analysis of navigational safety in vicinity of newly constructed
quay placed to the east of the island Ostrow Brdowski. The Quay is intended handling of large
steel structures. The Fast-Time simulation is performed to evaluate the safety of the navigation
passage through the fairway along the quay for the future use of vessels which length may
exceed 260 m. This kind of simulation method has been implemented to make a statistical
analysis based on a large amount of data, the collection of which would be very expensive and
time consuming using a Real-Time simulator.
Determination of the Risk of Location the Quay for Large Steel Components Handling in Vicinity of the Fairway Using the Fast-Time Simulation Method
1Maritime University of Szczecin, Poland
2Maritime University of Szczecin, Poland
DOI: DOI: 10.1515/aon-2018-0007
ABSTRACT
KEYWORDS
REFERENCES
[1] Arndal N., Yafiez M.A. Use of fast-time and real-time simulation in harbor design: The Dos Bocas case. Transactions on the Built Environment vol. 40, 1999.
[2] Gucma L. Modelling of risk factors for collisions of vessels with port and opensea constructions (in Polish). Maritime University of Szczecin, Szczecin 2005.
[3] Gucma L. The risk management at sea (in Polish). Maritime University of Szczecin, Szczecin 2009.
[4] Gucma L. New Mielno Port design – results by real time simulation study. Scientific Journals of the Maritime University of Szczecin, nr 38 (110), 2014
[5] Gucma S. Sea Traffic Engineering (in Polish). Okrętownictwo i Żegluga, Gdańsk
2001.
[6] Gucma S. Determination of maximal ship safe conditions for entrance to the
ports. Risk Analysis IV, C. A. Brebbia (Editor), 2004.
[7] Gucma S. (ed.) Simulation methods in marine traffic engineering (in Polish).
Maritime University of Szczecin, Szczecin 2008.
[8] IIRM AM. The construction of the wharf to LNG handling at the protection
breakwater of the external port in Świnoujście (in Polish). Project ordered by
Szczecin and Swinoujscie Seaports Authority SA, Szczecin 2007.
[9] IIRM AM. Navigation analysis for the bridge from the Ostrów Brdowski island.
Maritime University of Szczecin, Szczecin, 2013.
[10] Harbour Approach Channels Design Guidelines. PIANC Report PIANC Secretariat General, Brussel 2014.